Claim · CLM-017

Investment estimate: €7.9–8.9 billion at 2024 prices

Status: Officially proposed As of

Illustration: Luís de Camões Airport Observatory (original work). Not to scale; not the airport design.

The technical report estimates the investment in the new airport at between €7.9 billion and €8.9 billion, at 2024 prices.

deverá representar um investimento entre 7,9 mil milhões e 8,9 mil milhões de euros, a preços de 2024

Original wording (short quotation) — Portuguese Government (summarising ANA's technical report)

Record details

Record ID
CLM-017
As-of date
First seen by the observatory
Last verified
Form
Short quotation
Claimant (organisation or office)
Portuguese Government (summarising ANA's technical report)
Date the claim was made
Type of proposition
Forecast
Binding nature
Non-binding
Metric unit
EUR million
Price base / base year
2024 prices
Scope of the figure
The airport project in ANA's technical report. Whether it includes land, the military relocation, rail, the Third Tagus Crossing, regional roads, financing costs, inflation and contingency has not been stated in the sources reviewed.

Sources

  1. Luís de Camões Airport should represent an investment of between 7.9 and 8.9 billionPortuguese Government (XXV Constitutional Government) · · 2 — Official report, plan or statement Original (opens the issuer’s website)
  2. Two runways and 64 boarding gates: see what the new Luís de Camões airport will look likeJornal de Negócios · · 4 — Independent reporting Original (opens the issuer’s website)

Version history

Earlier versions are never overwritten. Each row is a snapshot recorded when an editor approved a change.

VersionRecordedStatus thenChange note
v1Status: Officially proposedFirst published

Verification

Fact-check stage
Source checked
Last verified
How it was checked
Checked against the cited primary source on 18 Oct 2026.

Report an error in this record