Claim · CLM-017
Investment estimate: €7.9–8.9 billion at 2024 prices
Status: Officially proposed As of
The technical report estimates the investment in the new airport at between €7.9 billion and €8.9 billion, at 2024 prices.
deverá representar um investimento entre 7,9 mil milhões e 8,9 mil milhões de euros, a preços de 2024
Record details
- Record ID
- CLM-017
- As-of date
- First seen by the observatory
- Last verified
- Form
- Short quotation
- Claimant (organisation or office)
- Portuguese Government (summarising ANA's technical report)
- Date the claim was made
- Type of proposition
- Forecast
- Binding nature
- Non-binding
- Metric unit
- EUR million
- Price base / base year
- 2024 prices
- Scope of the figure
- The airport project in ANA's technical report. Whether it includes land, the military relocation, rail, the Third Tagus Crossing, regional roads, financing costs, inflation and contingency has not been stated in the sources reviewed.
- Topic
- Costs and funding
- Institution
- ANA – Aeroportos de Portugal, Portuguese Government
Sources
Version history
Earlier versions are never overwritten. Each row is a snapshot recorded when an editor approved a change.
| Version | Recorded | Status then | Change note |
|---|---|---|---|
| v1 | Status: Officially proposed | First published |