Construction progress

Construction has not started. As of 18 October 2026 there is nothing to report on site, and this page says so rather than showing an invented progress bar.

Facts on this page as of · Corrections

Illustration — not to scale, not the airport design
Illustration: Luís de Camões Airport Observatory (original work). About this image

The July 2026 schedule targets construction from 2029 to 2033. Before works can begin, the environmental decision, acceptance of the complete application, financing and the release of the firing-range land (scheduled in phases by 2029) are needed. When contracts are signed and works begin, they will be recorded here with dated, sourced updates.

Scheduled construction steps

  1. 2026
  2. Event (happened)

    Replacement firing range announced in Alter do Chão

    Ministry of National Defence announces the location of the replacement military firing range.

    Military relocation · Status: Officially proposed

    Source: Ministério da Defesa Nacional

  3. Event (happened)

    Demilitarisation spending authorised (RCM 119/2026)

    Up to €4.5 million plus VAT authorised for demilitarisation work at the firing range.

    Military relocation · Status: Legally decided

    Source: Diário da República

  4. Today — 19 October 2026
  5. 2029
  6. Scheduled target

    Construction start target

    Construction to begin, per the July 2026 schedule.

    Construction · Status: Target / forecast · Scheduled

    Source: Portuguese Government (XXV Constitutional Government)

  7. Scheduled target

    Firing-range land released for the airport

    Phased release of the area needed for the airport.

    Military relocation · Status: Target / forecast · Scheduled

    Source: ANA – Aeroportos de Portugal (VINCI Airports)

  8. 2030
  9. Superseded

    First runway target (2024 plan)

    May 2024 target for the first runway; superseded by the July 2026 schedule.

    Construction · Status: Historical / superseded · Superseded

    Source: Portuguese Government (XXIV Constitutional Government)

  10. 2031
  11. Superseded

    Second runway target (2024 plan)

    May 2024 target for the second runway; superseded.

    Construction · Status: Historical / superseded · Superseded

    Source: Portuguese Government (XXIV Constitutional Government)

  12. 2033
  13. Scheduled target

    Construction completion target

    Construction to be completed by 2033, before tests and certification.

    Construction · Status: Target / forecast · Scheduled

    Source: Portuguese Government (XXV Constitutional Government)

Solid markers are events that have happened. Hollow markers are scheduled targets or deadlines: they are not guaranteed. Superseded targets are labelled and can be hidden or shown with the filters.

The approval path: done, under review, still to come

  1. 14 May 2024Site chosen by Council of Ministers resolutionDone
  2. 16 July 2025Interim report 1: stakeholder consultationDone
  3. 20 March 2026Placement at the eastern end validatedDone
  4. 16 July 2026Technical report deliveredDone
  5. 31 July 2026Environmental impact study delivered to APADone
  6. 28 September 2026Government questions the design (not an acceptance)Under review
  7. 16 January 2027Interim report 4: financial report dueScheduled
  8. by 16 January 2028Complete application dueScheduled
  9. —Public consultation and environmental decision (APA)No date set
  10. —Acceptance of the complete application under the concessionNo date set
  11. 2029Construction (target 2029–2033)Target only
  12. from 2035Opening (target: from 2035)Target only
Scheduled dates and targets are not guarantees. Data as of 18 October 2026, from the linked records. Graphic: Luís de Camões Airport Observatory (original work).
A soldier aims a rifle across sandy scrubland with pine trees.

A Portuguese Marine during a bilateral exercise at the Campo de Tiro de Alcochete on 14 January 2020 — the site's current military use, which must end before construction. U.S. Marine Corps photo.

“Wild Crocodile II (6051342)”, author: U.S. Marine Corps photo by Cpl. Kenny Gomez, Public domain, via Wikimedia Commons. Resized to 1,600 px wide.

What the documents say

Open questions

  1. Which designers, architects and contractors have been appointed?

    Open

    Why it matters

    Named firms and contracts are the first concrete sign that design and construction are moving from proposal to delivery.

    What is known so far

    ANA says a multidisciplinary team of more than 250 people works on the project. No design or construction contracts were identified in the sources reviewed.

    Source: ANA – Aeroportos de Portugal (VINCI Airports)