The approval path: done, under review, still to come

  1. 14 May 2024Site chosen by Council of Ministers resolutionDone
  2. 16 July 2025Interim report 1: stakeholder consultationDone
  3. 20 March 2026Placement at the eastern end validatedDone
  4. 16 July 2026Technical report deliveredDone
  5. 31 July 2026Environmental impact study delivered to APADone
  6. 28 September 2026Government questions the design (not an acceptance)Under review
  7. 16 January 2027Interim report 4: financial report dueScheduled
  8. by 16 January 2028Complete application dueScheduled
  9. —Public consultation and environmental decision (APA)No date set
  10. —Acceptance of the complete application under the concessionNo date set
  11. 2029Construction (target 2029–2033)Target only
  12. from 2035Opening (target: from 2035)Target only
Scheduled dates and targets are not guarantees. Data as of 18 October 2026, from the linked records. Graphic: Luís de Camões Airport Observatory (original work).

Record details

Record ID
MED-031
As-of date
First seen by the observatory
Last verified
Kind
Infographic
Permission status
Original work of the observatory
Copyright owner
Luís de Camões Airport Observatory
Creator
Luís de Camões Airport Observatory
Design vintage
Not a design image
Built-in infographic (original, generated from the records)
The approval path: done, under review, still to come

Verification

Fact-check stage
Source checked
Last verified
How it was checked
Generated from the published records; numbers and statuses update with them.

Report an error in this record