Completed and verified
Figure
Lisbon airport passengers in 2025
Status: Completed and verified
Milestone
Government letter flags outdated minimum specifications
Status: Completed and verified
In a letter to the concessionaire, the Government identifies the need to update the concession's minimum specifications.
Milestone
Stakeholder consultation report delivered
Status: Completed and verified
First of four interim reports of the complete application; more than 100 bodies consulted.
Milestone
Government responds to the consultation report
Status: Completed and verified
Government publishes the executive summary and confirms that minimum specifications need updating.
Milestone
Location validated at the eastern end of the range
Status: Completed and verified
Ministry agrees the placement and asks ANA to revise its traffic forecasts.
Milestone
Technical report delivered
Status: Completed and verified
ANA delivers the technical report: two runways, single terminal of about 500,000 m², 64 gates, 56 million passengers at opening.
Milestone
Design, cost and schedule presented in public
Status: Completed and verified
Public session in Lisbon: €7.9–8.9 billion at 2024 prices, opening from 2035, rail in 2034.
Milestone
Environmental impact study delivered to APA
Status: Completed and verified
About 5,000 pages delivered; APA process AIA 3982. No consultation dates on the register as of 18 October 2026.
Figure
Lisbon airport passengers in 2019
Status: Completed and verified
Figure
Lisbon airport passengers in 2020
Status: Completed and verified