Claim · CLM-014
Opening planned from 2035
Status: Target / forecast As of
According to the schedule presented in July 2026, construction should start in 2029 and finish by 2033, and the new airport is expected to open from 2035, after tests and certification.
a abertura do novo aeroporto esteja prevista a partir de 2035
Record details
- Record ID
- CLM-014
- As-of date
- First seen by the observatory
- Last verified
- Form
- Short quotation
- Claimant (organisation or office)
- Portuguese Government (summarising ANA's technical report)
- Date the claim was made
- Target date or horizon (as stated)
- from 2035
- Type of proposition
- Target
- Binding nature
- Conditional on other decisions
- Conditions and dependencies
- Depends on the environmental decision, acceptance of the complete application, financing and certification.
- Supersedes claim
- 2024 target: first runway by 2030, second by 2031
- Topic
- Schedule
- Institution
- ANA – Aeroportos de Portugal, Portuguese Government
Sources
Version history
Earlier versions are never overwritten. Each row is a snapshot recorded when an editor approved a change.
| Version | Recorded | Status then | Change note |
|---|---|---|---|
| v1 | Status: Target / forecast | First published |