Schedule
Milestone
Construction start target
Status: Target / forecast
Construction to begin, per the July 2026 schedule.
Milestone
First runway target (2024 plan)
Status: Historical / superseded
May 2024 target for the first runway; superseded by the July 2026 schedule.
Milestone
Second runway target (2024 plan)
Status: Historical / superseded
May 2024 target for the second runway; superseded.
Milestone
Construction completion target
Status: Target / forecast
Construction to be completed by 2033, before tests and certification.
Milestone
Airport opening target
Status: Target / forecast
Opening from 2035 after tests and certification. Not guaranteed.
Milestone
Reported longer programme: opening 2037
Status: Unverified
Reported as the concessionaire's longer schedule; primary source not yet identified.
Open question
Where does the reported 2037 opening date come from?
Media asset
Illustration: dates and deadlines
Figure
First runway target year (2024)
Status: Historical / superseded
Figure
Second runway target year (2024)
Status: Historical / superseded