Schedule

Illustration: Luís de Camões Airport Observatory (original work). Not to scale; not the airport design.
  • Claim

    Opening planned from 2035

    Status: Target / forecast

    According to the schedule presented in July 2026, construction should start in 2029 and finish by 2033, and the new airport is expected to open from 2035, after tests and certification.

  • Claim

    A longer programme with opening in 2037 has been reported

    Status: Unverified

    Contemporary reporting cited in the observatory's research baseline described 2037 as the concessionaire's longer schedule for opening. The observatory has not yet identified a primary document stating 2037.

  • Claim

    Construction planned from 2029 to 2033

    Status: Target / forecast

    Construction should start in 2029 and be completed by 2033, according to the schedule presented in July 2026.

  • Claim

    Financial report due on 16 January 2027

    Status: Target / forecast

    The next step in the application is delivery of the financial report on 16 January 2027, completing the four interim reports.

  • Claim

    Complete application due by 16 January 2028

    Status: Target / forecast

    The complete application, containing the final version of all reports, is to be delivered by 16 January 2028 at the latest.

  • Claim

    Government wants to bring the opening forward

    Status: Officially proposed

    The Government said it intends to keep working with ANA to identify ways to shorten the planned timescales and bring the airport into operation earlier than the calendar currently proposed by the concessionaire.

  • Claim

    Airport rail line to open in 2034

    Status: Target / forecast

    The new Lisbon–Airport rail line is to open in 2034, with a new station served by four tracks and three platforms and direct connections to long-distance trains.

  • Claim

    Lisbon–Madrid by high-speed rail in 2034

    Status: Target / forecast

    The Government mandated IP to bring forward the studies needed to deliver the Lisbon–Madrid high-speed link in 2034, with a journey time of about three hours.

  • Claim

    2024 target: first runway by 2030, second by 2031

    Status: Historical / superseded

    In May 2024 the Government said the first runway should be built in 2030 and the second in 2031.

  • Investigation

    From 2030 to 2035 (and 2037?): how the opening date moved

    In 2024 the first runway was due in 2030. In 2026 the airport opens 'from 2035'. A third date circulates without a primary source. The record, in order.

    · verified