Chart: how the opening date moved
As of
How the opening date moved
20282029203020312032203320342035203620372038
Reported, unverifiedopening
- May 2024 plan — first runway: 2030
- May 2024 plan — second runway: 2031
- July 2026 schedule — construction: 2029–2033
- July 2026 schedule — rail link: 2034
- July 2026 schedule — opening: from 2035
- Reported, unverified — opening: 2037