    Government responds to ANA’s technical report on the new Lisbon airport

    The Ministries of Finance and of Infrastructure sent ANA their response to the technical report. They ask for different demand scenarios, further demonstration of runway and taxiway configuration and full compatibility with Code F…

  • Source document

    Government responds to ANA’s consultation report and publishes it

    The consultation report, delivered on 16 July 2025, is the first of four interim reports in the complete application. More than 100 bodies were consulted. Of nine proposed changes to the concession's minimum specifications,…

  • Claim

    Government asks for different demand scenarios

    Status: Under review

    In its 28 September 2026 response the Government welcomed ANA's acknowledgement that its initial traffic projections were inadequate, but asked for different demand scenarios to test the robustness of the airport's sizing over the…

  • Claim

    Government asks ANA to demonstrate Code F compatibility

    Status: Under review

    The Government identified airside matters needing further demonstration: the configuration of the runways and taxiway network and its full compatibility with Code F aircraft, capacity and operational flexibility.

  • Claim

    Single terminal replaces the earlier Terminal 2 or satellite concept

    Status: Under review

    ANA's technical report provides for a single passenger terminal and no longer includes the Terminal 2 or satellite terminal of its initial report. The Government asked ANA to justify this and present a clear…

  • Claim

    The response is not acceptance of the complete application

    Status: Under review

    The Government stressed that its response to the technical report does not constitute formal acceptance of the complete application, which will be assessed under the concession contract.

  • Claim

    Financial report due on 16 January 2027

    Status: Target / forecast

    The next step in the application is delivery of the financial report on 16 January 2027, completing the four interim reports.

  • Claim

    Complete application due by 16 January 2028

    Status: Target / forecast

    The complete application, containing the final version of all reports, is to be delivered by 16 January 2028 at the latest.

  • Claim

    Government wants to bring the opening forward

    Status: Officially proposed

    The Government said it intends to keep working with ANA to identify ways to shorten the planned timescales and bring the airport into operation earlier than the calendar currently proposed by the concessionaire.