Target / forecast
Milestone
Construction completion target
Status: Target / forecast
Construction to be completed by 2033, before tests and certification.
Milestone
Airport rail line opening target
Status: Target / forecast
Lisbon–Airport line via the Third Tagus Crossing.
Milestone
Lisbon–Madrid high-speed rail target
Status: Target / forecast
IP mandated to deliver Lisbon–Madrid in 2034, about three hours.
Milestone
Airport opening target
Status: Target / forecast
Opening from 2035 after tests and certification. Not guaranteed.
Milestone
Financial report due
Status: Target / forecast
Fourth and last interim report of the complete application.
Milestone
Complete application due
Status: Target / forecast
Final versions of all reports, to be assessed under the concession contract.
Milestone
Firing-range land released for the airport
Status: Target / forecast
Phased release of the area needed for the airport.
Milestone
Construction start target
Status: Target / forecast
Construction to begin, per the July 2026 schedule.
Figure
Long-term passenger capacity
Status: Target / forecast
Figure
Strategic demand scenario for 2050
Status: Target / forecast