Target / forecast

Illustration: Luís de Camões Airport Observatory (original work). Not to scale; not the airport design.
  • Claim

    Firing-range land to be released in phases by 2029

    Status: Target / forecast

    The phased demilitarisation schedule provides for releasing the area needed for the airport by 2029.

  • Decision

    Opening target announced

    Status: Target / forecast

    Opening from 2035; the Government wants to bring it forward.

  • Claim

    Opening planned from 2035

    Status: Target / forecast

    According to the schedule presented in July 2026, construction should start in 2029 and finish by 2033, and the new airport is expected to open from 2035, after tests and certification.

  • Claim

    Construction planned from 2029 to 2033

    Status: Target / forecast

    Construction should start in 2029 and be completed by 2033, according to the schedule presented in July 2026.

  • Claim

    Growth to 85 million passengers a year

    Status: Target / forecast

    The airport could grow to 85 million passengers a year over the long term, according to the July 2026 presentation.

  • Claim

    Financial report due on 16 January 2027

    Status: Target / forecast

    The next step in the application is delivery of the financial report on 16 January 2027, completing the four interim reports.

  • Claim

    Complete application due by 16 January 2028

    Status: Target / forecast

    The complete application, containing the final version of all reports, is to be delivered by 16 January 2028 at the latest.

  • Claim

    Airport rail line to open in 2034

    Status: Target / forecast

    The new Lisbon–Airport rail line is to open in 2034, with a new station served by four tracks and three platforms and direct connections to long-distance trains.

  • Claim

    20 million rail passengers a year

    Status: Target / forecast

    The estimate is that 20 million passengers a year will travel to and from the airport by train.

  • Claim

    Lisbon–Madrid by high-speed rail in 2034

    Status: Target / forecast

    The Government mandated IP to bring forward the studies needed to deliver the Lisbon–Madrid high-speed link in 2034, with a journey time of about three hours.