Architecture and terminal
Milestone
Technical report delivered
Status: Completed and verified
ANA delivers the technical report: two runways, single terminal of about 500,000 m², 64 gates, 56 million passengers at opening.
Milestone
Design, cost and schedule presented in public
Status: Completed and verified
Public session in Lisbon: €7.9–8.9 billion at 2024 prices, opening from 2035, rail in 2034.
Open question
Which designers, architects and contractors have been appointed?
Open question
Which parts of the published images are illustrative, and which images belong to older concepts?
Open question
Will the single-terminal design survive the review?
Figure
Long-term passenger capacity
Status: Target / forecast
Figure
Passenger terminal area
Status: Officially proposed
Figure
Boarding gates
Status: Officially proposed
Figure
Contact boarding bridges
Status: Officially proposed
Figure
Aircraft stands
Status: Officially proposed