Decisions and approvals

What is actually approved? Only the site and the principle of replacing Humberto Delgado, plus preparatory land and demilitarisation measures. The design, environmental approval, financing, rail, roads and construction are not.

Facts on this page as of · Corrections

Illustration — not to scale, not the airport design
Illustration: Luís de Camões Airport Observatory (original work). About this image

Each card shows the most recent recorded decision, submission or official response for one part of the project. An official response or a submission is not an approval.

Legally decided: 3 · Under review: 3 · Officially proposed: 3 · Nothing decided: 1 · Target / forecast: 1

Every decision and official step

Decisions, submissions and official responses, newest first
DateStepInstitutionTypeStatus
Concession application: interim stageMinistries of Finance and of Infrastructure and HousingConcession procedure stepStatus: Under review
Government response to the technical reportMinistries of Finance and of Infrastructure and HousingMinisterial response (not an approval)Status: Under review
Environmental impact study submitted
AIA 3982
ANA – Aeroportos de PortugalSubmission by proponentStatus: Under review
Financing plan presentedANA – Aeroportos de PortugalGovernment announcementStatus: Officially proposed
Opening target announcedPortuguese GovernmentGovernment announcementStatus: Target / forecast
Rail link announcedPortuguese GovernmentGovernment announcementStatus: Officially proposed
Road plan announcedPortuguese GovernmentGovernment announcementStatus: Officially proposed
Technical report submittedANA – Aeroportos de PortugalSubmission by proponentStatus: Officially proposed
Demilitarisation spending authorised
RCM 119/2026
Council of MinistersCouncil of Ministers resolutionStatus: Legally decided
Placement at the eastern end of the range validatedMinistry of Infrastructure and HousingMinisterial response (not an approval)Status: Legally decided
Replacement firing range location announcedMinistry of National DefenceGovernment announcementStatus: Officially proposed
Preventive land-use measures
RCM 30/2026
Council of MinistersCouncil of Ministers resolutionStatus: Legally decided
Humberto Delgado to be fully replaced
RCM 66/2024
Council of MinistersCouncil of Ministers resolutionStatus: Legally decided
Site selected: Campo de Tiro de Alcochete
RCM 66/2024
Council of MinistersCouncil of Ministers resolutionStatus: Legally decided

The approval path: done, under review, still to come

  1. 14 May 2024Site chosen by Council of Ministers resolutionDone
  2. 16 July 2025Interim report 1: stakeholder consultationDone
  3. 20 March 2026Placement at the eastern end validatedDone
  4. 16 July 2026Technical report deliveredDone
  5. 31 July 2026Environmental impact study delivered to APADone
  6. 28 September 2026Government questions the design (not an acceptance)Under review
  7. 16 January 2027Interim report 4: financial report dueScheduled
  8. by 16 January 2028Complete application dueScheduled
  9. —Public consultation and environmental decision (APA)No date set
  10. —Acceptance of the complete application under the concessionNo date set
  11. 2029Construction (target 2029–2033)Target only
  12. from 2035Opening (target: from 2035)Target only
Scheduled dates and targets are not guarantees. Data as of 18 October 2026, from the linked records. Graphic: Luís de Camões Airport Observatory (original work).

What counts as an approval

  • Legal decision: a published legal instrument, such as a Council of Ministers resolution.
  • Environmental decision: APA’s declaration at the end of process AIA 3982 — not yet issued.
  • Concession acceptance: acceptance of the complete application under the concession contract — not yet given.
  • Not approvals: submissions by ANA, ministerial responses to interim reports, and announced targets.

Questions answered

Who is building and running the airport?

ANA – Aeroportos de Portugal, a VINCI Airports company that holds the concession for Portugal’s main airports, is the project proponent. Under the concession contract it must submit a complete application that the Government will assess. No construction contractors had been identified at the baseline date.

Source: Agência Portuguesa do Ambiente (SIAIA) Source: Portuguese Government — Ministry of Infrastructure and Housing Source: ANA – Aeroportos de Portugal (VINCI Airports) Permalink: Who is building and running the airport?

What is the ‘complete application’?

It is the package ANA must deliver under its concession contract to build the new airport. It is built from four interim reports — consultation (July 2025), selected site and environment, technical (July 2026) and financial (due 16 January 2027) — and must be delivered in final form by 16 January 2028 at the latest.

Source: Portuguese Government — Ministry of Infrastructure and Housing Source: Portuguese Government (XXV Constitutional Government) Permalink: What is the ‘complete application’?

What did the Government say on 28 September 2026?

It praised the technical work but asked ANA for alternative demand scenarios, further demonstration of runway and taxiway configuration and Code F compatibility, and a clear expansion strategy, including a justification for dropping the earlier second terminal or satellite. It stressed that the response is not formal acceptance of the application.

Source: Portuguese Government — Ministry of Infrastructure and Housing Permalink: What did the Government say on 28 September 2026?

What happens next, and when?

On the published calendar: the financial report on 16 January 2027 and the complete application by 16 January 2028. The environmental assessment runs separately at APA, with no consultation dates published at the baseline date. These are scheduled steps, not guarantees.

Source: Agência Portuguesa do Ambiente (SIAIA) Source: Portuguese Government — Ministry of Infrastructure and Housing Permalink: What happens next, and when?

Is a ministerial response the same as an approval?

No. The concession procedure does not provide for a formal decision on interim reports. The Government’s responses of March and September 2026 are comments and requests; the binding decisions come later, on the complete application and in the environmental decision.

Source: Portuguese Government — Ministry of Infrastructure and Housing Permalink: Is a ministerial response the same as an approval?

Is this an official website?

No. It is an independent observatory, not affiliated with ANA, VINCI Airports or the Portuguese Government. It uses no official logos and links every claim to a source.

Source: Portuguese Government — Ministry of Infrastructure and Housing Permalink: Is this an official website?

How do I report an error?

Use the contact form, or the ‘Report an error’ link at the foot of any record. Material corrections are published on the corrections page with the original statement, the correction and the date; nothing is silently erased.

Source: Portuguese Government — Ministry of Infrastructure and Housing Permalink: How do I report an error?